Government of Balochistan through Secretary Education Department V. Messrs campaigner associates (pvt.) Ltd. through Chief Executive and 2 others,

PLJ 2018 Quetta 30Balochistan High CourtCivil Law2018

Bench: Abdullah Baloch

Share on WhatsApp
2017 C L C 1298 [Balochistan] Before Muhammad Ejaz Swati and Abdullah Baloch, JJ GOVERNMENT OF BALOCHISTAN through Secretary Education Department ---- Appellant Versus Messrs CAMPAIGNER ASSOCIATES (PVT.) LTD. through Chief Executive and 2 others ----Respondents R.F.A. No.22 of 2009, decided on 2nd May, 2017. Arbitration Act (X of 1940) --- ----Ss. 20 & 33---Award by umpire made rule of the court ---Agreement between the parties for completion of construction project ---Appointment of empire in wake of disagreement between the parties to appoint Arbitrators and no objections was raised by the appellant (Provincial Government) in the proceedings of the Court ---Scope ---Appellant/Provincial Government contended that no claim of payment of extra work could be agitated as per the undertaking of the respondent/contractor and thus award of the umpire was unjustified--- Respondent/contractor contended that they completed work to the entire satisfaction of the Government but was denied payment without reason---Respondent/contractor further submitted that the award by the umpire was justified and the umpire was appointed with consent as parties had failed to appoint Arbitrators ---Validity ---Record revealed that parties had suggested names of Arbitrators, but agreement was not arrived at, thus under the circumstances, Trial Court with consent of the parties nominated the umpire to make award independently within 30 days by providing opportunities to both the parties in accordance with law ---Record further trans pired that both the parties had put their claims before the umpire who, after hearing both the parties, passed award-- -Award was submitted before the Trial Court and the parties were directed to file their objections, if any, however, counsel for the respondent appeared before the Trial Court and raised no objection over the final award and despite of several opportunities, the appellant (State) had failed to file any objections as required under S.33 of Arbitration Act, 1940---Said order of the Trial Court was not assailed by the appellant before the appellate forum which attained finality, as such, the contentions of appellant with regard to non- providing opportunity of filing of objections was not tenable ---In view of provisions of S.33 of Arbitration Act , 1940 the appellant had failed to comply with the provision of law ---Findings of the umpire showed that the respondent/contractor had completed the work to the entire satisfaction of the department --- Department had never raised any objection regarding the performance of work ---Contract agreement being in existence, the work was completed on the instructions of Provincial Government through its department, therefore, Government could not absolve itself from the liability ---Impugned judgment and decree passed by the Trial Court did not suffer from misreading or non- reading of evidence ---Appeal was dismissed accordingly. Muhammad Saleem Baloch for Appellant. Ms. Shehnaz Rana and Rehmatullah Barech for Respondent No.2 Date of hearing: 17th April, 2017. JUDGM ENT ABDULLAH BALOCH, J. --- This judgment disposes of R.F.A. No.22 of 2009 filed by the Government of Balochistan Education Department, through Additional Advocate General Balochistan, against the judgment and decree dated 28th February, 2009 (hereinafter referred as "the impugned judgment and decree") passed by learned Civil Judge- V, Quetta (hereinafter referred as "the trial Court"), whereby the Award dated 6th August, 2008 passed by the Umpire was made as rule of the Court (hereinafter the Award dated 6t h August 2008 is referred as, "the Award"). 2. Facts of the case are that the respondent No.1 filed an application under Section 20 of the Arbitration Act for arbitration award with the averments that the respondent No.1 is registered Company under the Com panies Act, having its business under the name and style of M/S Campaigner Associates (Pvt.) Ltd. 75- E Maulana Shaukat Ali Road, M.A. Johar Town Lahore; that an agreement for completion of contract of project "Construction of Additional 6 Workshops, 6 Clas s Rooms and Hostel for 200 Students in the Government Polytechnic Institute for Boys at Sariab Road, Quetta (Package No.2) was executed, whereafter the work was completed to the entire satisfaction of the Engineer Incharge, who has been defined under the terms and conditions of the agreement as M/S Unique Associates, who verified all the bills, but it was unfortunate on the part of the appellant (Government of Balochistan) and other respondents not to follow the terms and conditions of the agreement and denied the payments payable to the respondent No.1. It is pertinent to point out that on different occasions the payments were determined in favour of the respondent No.1, but the same were withheld without any reason and rhyme, which is also disturbed flow of finance for the execution of the job, resultantly the respondent No.1 was left with no alternate, but to invoke the jurisdiction of this Court in C.P. No.1114/1999, which petition was disposed of vide judgment dated 19th April, 2000 in the following terms: (i) The agreed amount regarding which there is no dispute at the moment be paid to the petitioner. (ii) For disputed amount the mechanism provided in the contract agreement be followed. (iii) The work shall not be discontinued/suspended without following the provisions contained in Clause 55 of the contract. (iv) In view of the serious apprehensions of Project Director that petitioner may not complete the Project after getting the amount in question could be met by obtaining surety in accordance with con tract agreement. (v) The requisite certificate for the work done which is not disputed shall be issued without further loss of time. (vi) The bid price package No.1 and package No.2 shall remain within the agreed limits of Rs.61,433,439.58 and Rs.55,455,399.66 respectively and it shall have not bearing on the extra work done by the petitioner with the mutual consent of the respondents, but total price shall not cross the limits of Rs.61,433,439/58 and Rs.55,455,399/66 (excluding extra work)." The respondent No.1 further averred that in compliance with the above order, he followed the procedure laid down under the agreement and on 28th September 2004 served a legal notice to the appellant with the request for appointment of the Arbitrator on the panel of the Arbitration Committee and the respondent No.1 suggested his nominate as Mr. M.M. Chandion, Ex-Chief Engineer, House No.12 Mehran House near citizens Colony, Hyderabad, but the appellant and the respondent No.2 did not rise to the occasion with the target period of the notice to appoint their nominee. The respondent No.1 prayed for appointment of the Arbitrators in the following terms: a. Payment under the B.O.Q. items amount to Rs.5,948,869.65 b. Extra Payment for new items amounting to Rs.3,448,843.57 cropped up during the execution of the job for which no rate was available. c. Compensation at the rate of 16% per annum for delaying the payment actually done to the petitioner till the filing of this application for Rs.14,703,233.11. d. During the execution of the job on different occasions the work was stopped and the petitioner had to suffer losses on account of overhead charge and Idle T&P for Rs.3,541,457.30. e. Loss sustained by the petitioner amounting to Rs.751,600.00 due to incident on 08.10.2001 wit hin the premises of the job in question. f. Litigation charges. g. Any other claim at the time of arbitration proceedings. In the last the respondent No.1 prayed that: (a) The respondent No.2 may kindly be directed to file the agreement for the work in dispute in this Court. (b) The respondents may kindly be directed to nominate their nominee on the panel of the Arbitration Committee and the nominee so nominated along with the nominee of the petitioner, may kindly be appointed as arbitrators to adjudicate upon the dispute and file the award in this Court on the date fixed by this Court. 3. It appears that, the appellant filed rejoinder to the application and contested the same. After filing rejoinder, the parties were directed to file the names of their resp ective arbitrators, to which both the parties suggested the names of different arbitrators, but no agreement was arrived at, thus under the circumstances, the trial Court with the consent of both the parties nominated Mr. Sakhi Sultan, Advocate Supreme Court as Umpire, to make award independently within 30 - days after providing opportunities to both the parties in accordance with law. In pursuance of such order, the parties have put their award and facts before the umpire, who after hearing both the parties passed a common award dated 6th August 2008, the relevant portion is reproduced hereinbelow: "In view of the facts and circumstances explained hereinabove, the Contractor is entitled to their relief claimed for, except the amount of loss being occurred due to the law and order situation and the award is given in the following manner: S.No. Description of claim. Amount of Claim 1. Payment of B.O.Q. Items (less paid/Not paid) Rs.9,359,433.09 2. Extra Works. Rs.3,141,740.14 3. Use of SR Cement. Rs.283,182.00 4. Loss occurred due to the law and Order situation Not entitled. 5. Idle Charges suspended period Rs.6,738,398.15 6. Interest on delayed payments Rs.1,78,00,863.00 7. Compound Interest. Not entitled. Grand total of claim Rs.3,73,23,516/ - 4. After passing of final award by Umpire, the same was filed before the learned trial Court, hence the parties were directed to file their objections, if any, to which the learned counsel for the respondent No.1 appeared before the Court and raised no objection over the final award, while despite several opportunities the State has failed to file any such objection. Hence, under the circumstances the Award dated 6th August 2008 was made as Rule of the Court, vide impugned judgment and decree dated 28th February 2009. 5. Learned Additional Advocate General contended that Arbitration Award passed by Arbitrator Malik Abdul Rauf and umpire Sakhi Sultan, Advocate have failed to consider the facts and circumstances of the case; that the app ellant specifically raised objections in his rejoinder; that he was not a party to the agreement as agreement was executed between respondents Nos.1 and 2, but this point was not considered by the Arbitrator, umpire, as well as by the learned trial Court; that the Arbitrator, umpire and the learned trial Court have failed to consider the facts of the case; that the respondent No.1 has given undertaking through written reference in which he stated that he will not claim payment of extra work, but in spite of this fact no one considered this point; that the umpire was appointed by the learned trial Court without the consent and permission of the appellant; that according to clause 21- 1 of the agreement executed between the parties, in which it was decided that all the disputes arising in connection with the present contract and which cannot be amicably settled between the parties, shall be finally settled under the rules of conciliation and arbitration of international chamber of commerce by one or more arbitra tors appointed in accordance with rules; that all the work which was completed by the contractor and payment of that work has been paid to the respondent No.1 and the award is not sustainable; that the Arbitration Award was made as rule of Court by the lea rned trial Court in a hazard manner which resulted in miscarriage of justice; that there are sufficient illegalities and irregularities in the award which is liable to be set aside. 6. Conversely, the learned counsel for the respondents strongly opposed the arguments so advanced by the learned counsel for the appellant and contended that the respondents had carried out the entire contractual work according to contract agreement executed between the parties; that the appellant have failed to discharge their liabilities; that the appellant was approached by the respondents for settlement of dispute through amicable settlement and arbitration, but the appellant delayed the matter by one pretext or the other; that ultimately the respondents after issuing legal n otice to the appellant and on failure of reply of the same the respondents have filed an application in the Court for appointment of arbitrators, which was contested by the appellant and with consent of the parties the learned trial Court nominated Mr. Sakhi Sultan, Advocate as umpire to make award independently; that the umpire was appointed with the consent of the appellant and thereafter the award was passed; that the appellant have failed to file objections on the award made by the umpire; that the lear ned trial Court had rightly made the award as rule of Court. 7. Heard the counsel for the parties and perused the record with their valuable assistance the record reveals that the dispute as stated above arose between the parties, initially the parties approached this Court under C.P No. 1114 of 1999, however, the petition was disposed of vide Judgment dated 19th April, 2000 with certain terms as stated above in para No.2 and in compliance of the said order the respondents have issued a legal notice to the appellant with the request for appointment of arbitrator on the panel of arbitration Committee and respondent No.1 suggested his nominate as Mr. M.M. Chandio ex Chief Engineer, but the appellant and respondent No.2 did not rise to the occasion with the tar get period of notice to appoint their nominees. 8. The record further reveals that due to failure of the appellant and respondent No.2 the respondent No.1 filed an application before the Arbitration Court for appointment of Arbitrator on the terms and conditions given therein; it is further transpired from the record that the said application was contested by the appellant by means of filing rejoinder and thereafter the parties were directed to file the names of their respective Arbitrators, to which both t he parties suggested names of different Arbitrators, but no agreement was arrived at, thus under these circumstances, the learned trial Court with consent of the parties nominated Sakhi Sultan, Advocate Supreme Court as umpire to make award independently w ithin 30 (Thirty Days) days after providing opportunities to both the parties in accordance with law. The record further transpires that both the parties have put their claims before the umpire who after hearing both the parties passed a common award on 6t h August, 2008. 9. The record further indicates that the award was submitted before the learned trial Court and the parties were directed to file their objections, if any, however, the learned counsel for the respondent No.1 appeared before the trial Court and raised no objection over the final award, while despite of several opportunities, the appellant (State) has failed to file any such objections as required under Section 33 of Arbitration Act, 1940. For convenience relevant provisions of Section 33 of Arbitration Act, 1940 is reproduced as under: - "33. Arbitration agreement or award to be contested by application.-- Any party to an arbitration agreement or any person claiming under him desiring to challenge the existence or validity of an arbitration ag reement or an award or to have the effect of either determined shall apply to the Court and the Court shall decide the question on affidavits: Provided that where the Court deems it just and expedient, it may set down the application for hearing on other e vidence also, and it may pass such orders for discovery and particulars as it may do in a suit." 10. We have also consciously observed that despite several opportunities the State counsel was failed to file objections over the award despite of the fact tha t it reflects from the order sheet dated 5.09.2008 of the trial Court last opportunity was afforded to the D.A for State for filing of objections on the next date fixed for hearing i.e. 20.9.2008 and order sheet dated 20.9.2008 shows that the D.A was prese nt and failed to file objections and sought further time for filing of objections which was opposed by the other side and ultimately the right of appellant was struck off for filing of objections. 11. The record further reveals that the said order was not assailed by the appellant in the appellate forum which attained finality, as such, the contentions of learned counsel for the appellants with regard to non- providing opportunity of filing of objection is not tenable and in view of the provisions Section 33 of Arbitration Act the appellants have failed to comply with. 12. The perusal of Arbitration Award passed by the learned Arbitrator indicated that after proper opportunity of hearing and participation of parties the learned Umpire had rightly passed the award in accordance with law and thereafter the same award was made as rule of Court in accordance with law wherein the parties were represented by their counsel and the appellant was duly represented by the learned District Attorney namely Ms. Farhat Shameem, as such the appellant cannot say the judgment and decree was passed by the learned trial Court in their absence. 13. According to findings of the umpire the Contractor/respondents has completed the work to the entire satisfaction of the department and the department never raised any objection regarding the performance of work, since the contract agreements are in existence and the work was completed on the instruction of Government of Balochistan through Education department, therefore they cannot absol ve themselves from the liability simply on the ground that the project in question has been wound up. The work so carried out by the respondents they are entitled to relief claimed for. The learned Additional Advocate General has failed to point out any ma terial illegality or irregularity in the impugned judgment and decree passed by the learned trial Court. In view of the above discussion we are of the considered view that the impugned judgment and decree passed by the learned trial Court does not suffer from misreading and non- reading and mis -appreciation of evidence, neither ridiculous nor perverse or suffers from any infirmities to be interfered by this Court, as such the appeal is devoid of merits and is hereby dismissed. The parties are directed to bear their own costs. MQ/77/Bal. Appeal dismissed.
This judgment is reproduced from a publicly available source for informational purposes and does not constitute legal advice. If you believe this listing contains an error, let us know.

Related judgments

What happens when a suit is hit by Section 11 of CPC

PLJ 2012 Quetta 19 ยท Balochistan High Court ยท 2012

Can the property be attached during trial?

PLJ 2011 Quetta 105 (DB) ยท Balochistan High Court ยท 2011

Latest Judgment in a Defamation Case

PLD 1981 Kar. 515; Mazhar Valjee v. Sher Afghan Khan Niazi 2004 YLR ยท Balochistan High Court ยท 1981

Danae International Corporation V. M.V. Camel (Ex-Camelot) and another,

PLJ 2022 Quetta 78 ยท Balochistan High Court ยท 2022

A.C/SDM V. Mehrullah and another, Sui Southern Gas Company V. Mehrullah Khan and another,

CLC 2020 1680 ยท Balochistan High Court ยท 2020